Corrosion Protection Case Study
A major Gulf Chemical Plant
Texas, USA |
|
| |
In 2004, Brand (formerly Protherm) undertook a major CUI Project at a prominent Gulf Coast Chemical facility. Two 250+ foot towers were scheduled to be worked on simultaneously for CUI maintenance during a 28 day outage. Brand was responsible for stripping all of the existing insulation, blast cleaning all exposed surfaces, applying Thermal Spray Aluminum (TSA) to all surfaces and re-insulating the towers. The application of TSA required
special scaffold design and the construction
of kick-outs to facilitate the safe staging of
the bulky TSA equipment at staggered
heights on the tower structure. Brand
also provided full encapsulation of the towers to
|
|
prevent the escape of fugitive blast residue which could affect other personnel working in the area and potentially damage adjacent equipment. The containment was also necessary because the work area required dehumidification to preserve the very demanding quality of surface preparation necessary for a successful TSA application. Brand completed this highly critical project on time, within budget, and with zero safety incidents. This was the first project of this kind at the owner’s site and our success established us as the contractor of choice on all future projects of this nature.
|
|

© 2010 Brand Services, LLC All Rights Reserved.